HV Connections and Large Embedded Generators

Connecting to the High Voltage (HV) electricity network is a different process from connecting to the Low Voltage electricity network. CEOP8079: Connection Process Guideline outlines the end-to-end process for any connection onto Essential Energy’s High Voltage network.

HV Connection Types:

  • Chapter 5A - Generators less than 5MW (AEMO registration exempt)
  • Chapter 5 – Generators greater than 5MW (AEMO registration required)
  • Loads - Greater than 1.5MVA or modifications to existing HV connections
  • HV connected premises with zero-export behind the meter generation.

All enquiries for connection to the HV network are submitted within the Essential Connections Portal. All Connection Applicants must register for access to the Essential Connections Portal as a High Voltage Customer (Registering as a user for Major Connections projects). Registrations will be processed within five business days. Refer to Guide to registering to use Essential Connections - Major Network Connections.

Once registered with the Essential Connections Portal, Connection Applicants will need to submit a Preliminary Enquiry. This includes specific company and project connection information. Refer to the User guide: How to submit a Preliminary Enquiry.

A Preliminary Enquiry Response will be provided by Essential Energy with further connection details. Further information can be found in the Chapter 5A Information Package.

The Preliminary Enquiry key objective is to determine a single preferred connection option. Once the Connection Applicant chooses their preferred connection option, Essential Energy will respond with a Detailed Connection Enquiry (Chapter 5) or Connection Investigation Response (Chapter 5A) providing greater detail and specific network augmentation requirements.

A Connection Applicant may request Essential Energy to provide a Detailed Response under clause 5.3A.8(c) of the National Electricity Rules (NER) to its enquiry.

A price guide for the cost associated for this are listed within CEOP8079 Connection Process Guideline Annexure A – Connection Services Charges.

On submission of the Preliminary Enquiry, we recommend that Connection Applicants communicate with Essential Energy through the Essential Connections Portal.

Approximate Timeline is shown below, noting time and cost is greatly dependent upon the experience and qualifications of consultants engaged.

Process stage Activity CHAP 5A CHAP 5
Stage 1 Connection Application Preliminary Enquiry 1 month 1 month
Stage 2 Detailed Connection Enquiry / Connection Investigation Response 2 months 2 months
Stage 3 Connection Application – Network Studies 6-9 months 10-15 months
Stage 4 Contract Development 4-6 months 10-15 months
Stage 5 Delivery - Detailed Design / Construction 9-12 months 9-15 months
Stage 6 Commissioning / Energisation 2-3 months 2-4 months
Stage 7 Operations and Maintenance Ongoing Ongoing
Overall timeline Estimated end-to-end duration 2-3 years 3-5 years

Steps to take prior to submitting your enquiry

Further information

Contact the Major Network Connections Customer Manager at [email protected], or call 132391 during normal business hours.

Documents relating to HV connections and embedded generators

Avoided Transmission Use Of System (TUOS) Methodology

Download the Register of completed embedded generation projects

Find out about Emergency backstop and SCADA requirements for HV embedded generation